President DiPasquale and Robert Trombley met today with the contractors to kick off the Moore Renovation Project. As we all know, the starting date was August 9 and these are the projected dates for each phase of the project:
Phase I Completion of South Side - projected to be August 14, 2020
Phase II Completion of North Side - projected to be August 20, 2021
Total Project Completion should be October 19, 2021
We will continue to provide updates on the web and are very confident our project is moving along at a good pace.
*************************************************************
Fly Around Video of Moore Renovation Project - click
HERE to view video.
Message from President DiPasquale:The Moore Building Restoration/Renovation Project (AKA Clinton 2020) will begin approximately May 20, 2019 with an expected completion date of October 2020. The restoration will include new exterior insulation and finish on the façade, 464 new energy-efficient windows, 20 exterior doors, 10 interior doors as well as replacement of balcony and window railings to match the original architectural style.
This 107-year old building will also have the verandas repaired and/or rebuilt as well as repair of the columns on both verandas. New loading dock, exterior concrete stairs, veranda railings, as well as electronic access controls are all included in this nearly $12 million renovation.
Visit this page often to find out what is happening with the project and when offices will be relocating. We appreciate everyone's patience as we move forward with the transformation of this historical site.
Office Relocations:
Processing Center; Stafford Building, Room 137
Jenny Szalkowski, Typist
Admissions and Financial Aid
Stafford Building, Room 103T
Ania Miarka-Grzelak, Dean of Enrollment Management
Mary LaPierre, Director of Financial Aid
Donna Dixon, Admissions Advisor
Paula Brooks, Financial Aid Advisor
Jamie Dupell, Student Enrollment Specialist
Kayla Mucia, Administrative Assistant
Keri Denchick, Typist
Administration/Finance/Bursar's Office
Stafford Building, Room 102T Mary LaValley Blaine, Controller (224M)
Holly Barcomb, Assistant Bursar
Michelle Drollette, Staff Accountant
Registrar's Office
Stafford Building, Room 302T Jonathan Reid, Registrar
Dana Martineau, Typist
Counseling and Advisement
Stafford Building, Rooms 311T/315T
Chrisa O'Connell, SSS Coordinator
Wendy Grossmann, SSS Counselor/Advisor
Carla Wells, Typist
Student AffairsMoore Building, Room 113M
John Borner, Dean of Student Services
Institutional ResearchMoore Building, Room 205M
Jessica Aubrey, Data Analyst
Business Office/Purchasing
Moore Building, Room 103M
Darlene McPherson-Burnham, Staff Accountant
Kelly Dragoon, Purchasing Clerk
Human ResourcesMoore Building, Room 204M
Cheryl Lawrence, HR Associate
Instructional TechnologyMoore Building, Rooms 420M/421M
Faith Carter, Systems Programmer/Analyst
Darcy Purick, Technology Coordinator
David Scott, Network Administrator, (409M)
Academic Affairs
Moore Building, Room 405M Dr. John Kowal, Vice President
Barbara Golden, Administrative Assistant
Karen Case, Instruction Designer, (212T)
Faculty Relocations:
Carey Goyette/Jarrod Cone -
513MLori Robinson/Denise Coughlin -
508MTom Mandeville/Chris Drennan -
524MMaggie Courson/Kelly Misner -
512MStephen Young/Cody Miller -
519MDiane Parmeter/Julie Hanson -
515MJeff Meyers/Jeff Chase -
516MAngela Barnaby/Vicky Sloan -
517MDonna Lynch/Margaret Bolster -
509MMike Zerrahn/Shawn Irland -
514MJune Foley -
520M
Catherine Eloranto -
303MNurse's Office
Stafford Building, Room 107T
Sandra Marland, PT Nurse
Campus Life and Career ServicesStafford Building, Room 109T
Sarah McCarty, Director of Campus Life
Derek Payne, Career Services Coordinator
President's Office
Moore Building, Room 233M Ray DiPasquale, President
Tammy Villanueva, Assistant to President
Center for Community & Workforce Development (CCWD)Moore Building, Room 412M Angela Kelley, Development Specialist
Nancy Simpson, PT Typist